In progress
Our compliance notice issued in March 2018 dealt with maintenance matters.
Our assessment of these matters is set out in the stakeholder notice below.
We intended to inform ourself whether Aurizon Network was complying with the approved 2016 access undertaking (UT4) in light of Aurizon Network’s announcements that it was changing its maintenance practices.
In March 2018, we sent Aurizon Network a notice requesting information on its compliance with UT4. Stakeholders were also invited to provide any relevant information.
Aurizon Network provided information as requested by 20 April 2018. The Queensland Resources Council (QRC), Pacific National and Aurizon Coal also provided information within the same timeframe.
Date | Action |
---|---|
22 March 2018 | QCA issued a compliance notice to Aurizon Network |
26 March 2018 | QCA invited stakeholders to provide relevant information |
20 April 2018 | Aurizon Network responded to the compliance notice
Stakeholders provided information |
21 May 2018 | QCA provided a progress update |
21 September 2018 | QCA issued a stakeholder notice and update |